Avellanas Spent 2026 Getting Its Roads Rebuilt, One Approach at a Time

How many times has the drive to Playa Avellanas changed since January? Counting only the dated notices, at least six. Each one moved the detour, closed a stretch, or shifted the work to another part of the route. By late October the Municipalidad de Santa Cruz had worked its way along the Hernández approach and sent its machinery to the other road in, the stretch between Avellanas and Paraíso.

Through all of this, the beach end has stayed the fixed point. Lola's kept serving, the surf schools kept booking lessons, and a newer French kitchen has been taking reservations. This year, the drive has been the part of an Avellanas day most likely to change.

The Hernández Approach, Notice by Notice

The larger project is the one the municipality calls Hernández–Pinilla. It follows route C-05-03-067, and the municipality lists the investment at ₡897,000,000. The route runs past the main entrance to Hacienda Pinilla and toward San José de Pinilla. Most of the closure notices along the way were relayed by the community site Upe, which has posted bilingual updates since the first detour went up.

The dated record runs like this:

  • January 21: The main Hernández–San José de Pinilla road closed, and drivers were sent to a marked alternate route. Updates through late January noted drainage delays near Hacienda Pinilla's main entrance, plus a daytime closure of the alternate route itself, from 8 a.m. to 3 p.m., while it was being improved.
  • February 4: A municipal update covered bridge and drainage work on what that notice called the Hernández–Paraíso project.
  • April 17: Upe reported major excavation on the road toward San José de Pinilla, with a risk of temporary closures, provisional passage, and work expected to continue until June 30.
  • May 30: The municipality started repairing the alternate route to Pinilla, the road that had been carrying the detoured traffic, with regulated passage.
  • June 12: Trivisión reported that the project was in a technical pause for weather and quality-control processes. Asphalt was due to start the following week on a first section of 1.6 kilometers.
  • August 4 to 11: The road was closed from Hernández to Base 2 de Hacienda Pinilla for paving and road markings, coordinated by the municipality's Unidad Técnica de Gestión Vial Municipal.

In the first half of the year, the detour itself needed repairs. By August, there was pavement and paint on at least part of the main route.

What the August Update Says Is Still Underway

The municipality's most recent progress note on the project is dated August 18 and was updated on August 19. It opens with "Se continúa con la ejecución," which says the work is still being carried out. The note describes fill going in around a second box culvert, subbase being laid, and a stabilized base expected that same week.

That August note and the June paving report describe different stages. Trivisión's 1.6 kilometers was the "primer tramo," the first section. The August work on a second culvert fits a project being finished one segment at a time, with paving on one stretch while the next still has an open trench. Anyone who drove the paved part in August and assumed the whole route was done would have found base work further along.

The August note adds one detail that matters to anyone with a gate or a shopfront on the route. Crews were building concrete shoulders and driveway access for homes and commercial spaces along C-05-03-067. So the work reaches past the travel lanes to the edge of each property it passes.

The municipality has not published an overall completion date. Its last public status still describes the project as in execution.

October Moves the Machinery to the Paraíso Side

On October 3, Upe posted that municipal machinery would begin repairing the stretch between Avellanas and Paraíso, work that rain had held up. The notice asked residents for patience while it was underway.

This is the other way in. For much of the year, the Paraíso side has been the natural alternative whenever Hernández–Pinilla had a closure. Since early October it has had work of its own. This is a repair job, separate from the Hernández paving, and the October notice gives no end date.

The municipality spent the first eight months on the Hernández approach, from detour to drainage to culverts to asphalt, and then turned to the Paraíso side as the rains went on. For anyone driving in from Tamarindo, Villarreal or Huacas, the better route has changed from one month to the next. November opens with active work on the southern approach and an unannounced finish on the northern one.

The Beach End Kept Its Schedule

The places at the end of these roads have kept to much the same routine all year.

Lola's is still the anchor on the sand. It serves breakfast, lunch, dinner and drinks, with beach loungers and hammocks, and its menus are labeled 2026. Visitor reviews run through July 2026. Its current listing shows 9 a.m. to 7 p.m. daily and says parking is available, though hours can change with the season.

Avellanas Surf School is Lola's beach-based surf provider. It rents shortboards, longboards, soft-top boards and boogie boards. The school's own site offers lessons from beginner to advanced and carries a publication date of October 23, 2026, which counts as a fresh sign of life in a quiet month.

Avellanas Soul Surf School works out of Cabinas Las Olas. It lists private lessons at US$85 and group or children's lessons at US$70, and takes bookings by phone and WhatsApp.

Dreamsea describes its Avellanas surf house as open all year. Alongside surf lessons and board hire, it runs daily yoga, priced at US$15 for one session or US$40 for three group sessions. That makes it one of the easiest walk-in classes along this stretch of coast.

Soulshine runs an all-day restaurant with brunch and a contemporary Middle Eastern dinner menu. Its wellness page also lists a Monday 7 a.m. yoga class that is free for hotel guests, with donations welcome.

La Cabane is the newest name in this group. Two brothers opened it with a story rooted in the South of France, where, in their words, "life follows the rhythm of the sea, the sun, and those long, lingering meals that never seem to end." La Cabane takes table reservations online. It also offers a chef-at-home and events service, which helps on an evening when the drive in is the last thing anyone wants.

Breakfast and a loaned board at Lola's, a group yoga class at Dreamsea, a Middle Eastern dinner at Soulshine and a booked table at La Cabane can all fit into one Avellanas day without leaving the beach.

Planning a November Day Around the Work

Checking two sources before leaving covers most of what can go wrong.

  1. The municipality's project page. The Hernández–Pinilla update on the Municipalidad de Santa Cruz site is where official progress on the main project is posted.
  2. Upe's road notices. In 2026, closures were usually posted on Upe with a date range. The August Base 2 closure, for example, ran a stated seven days.
  3. The restaurant itself. Message or book the place you're heading to before you drive. Listed hours and real hours can drift apart in the green season, and La Cabane's online booking already makes this a two-minute step.

Rain has been the biggest variable in the schedule. It stopped the Hernández work in June and held up the Paraíso repairs before October. Late-season afternoon storms are the likeliest reason a planned closure will run long.

If you own a home on either approach, or you've been weighing the drive time from Avellanas to Tamarindo, Huacas or Hacienda Pinilla, our team at Flamingo Beach Realty keeps track of how this corridor is changing. We're happy to share what we're seeing on the ground. Contact Us whenever a question about the area comes up.